Our Design Engineers overlaid a 3D scan of the building with the new structure to ensure correct fitment and that it was physically able to be installed.

Due to the large size of the new bracing, much steelwork needed to be welded onsite. Our skilled fabricators did an amazing job under difficult conditions.

Working on the University grounds under Naylor Love, safety was of the utmost importance. Difficult crane lifts were required, which our experienced Engineers completed without incident.

Co-ordinating work with other trades, the installation needed to be carefully planned and managed. The success of this project showcases our capability to deliver high-quality projects safely.